Regional Public Journalism
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Hanford's Tricky And Long-Shuttered Plutonium Finishing Plant Is Now Officially Demolished

CH2M HILL Plateau Remediation Company
Hanford's shuttered Plutonium Finishing Plant has not produced its titular plutoium "buttons" since it closed in 1989, but crews just finished the main demolition.

The large plant that produced two-thirds of the United States’ Cold War-era plutonium no longer exists. 

Crews at the Hanford site recently finished demolishing the tricky Plutonium Finishing Plant’s main processing facility in southeastern Washington. 

But the demolition gave contractors some real trouble.

From 1949 to 1989, the massive plant’s job was to turn caustic liquids containing plutonium into solid plutonium “buttons,” as they were known. The finished buttons were about the size of hockey pucks and were used for America’s nuclear weapons. 

The main plant was about 500 feet long and 47 feet high.

Demolition started on the plant — called PFP by locals — more than 20 years ago. But as the public media Northwest News Network has reported, it didn’t go as planned as increasingly difficult parts of the plant were demolished. 

Credit U.S. Department of Energy
/
U.S. Department of Energy
The site of Hanford's Plutonium Finishing Plant as crews finalized the main demolition in February 2020.

In summer 2017, plutonium contamination was detected escaping the demolition site.

Officials with the U.S. Environmental Protection Agency were catching drifting particles on what looked like large metal pizza pans out near a public highway. Then some more contamination was found on workers’ parked cars. Some 42 workers were even contaminated. They had ingested small amounts of plutonium.

In January 2018 the demo project was shut down by Washington state’s Department of Ecology and the EPA for more than a year, while officials worked on better ways to protect workers and the environment. Some lower-risk work was allowed to continue during that time.

Poor communication was found to be contributing to the escape of contamination from the site.  

The high-risk demo began again last November. 

In all, crews removed more than 13,000 tons of debris into Hanford’s central dump for permanent disposal. The project missed it’s Tri-Party Agreement — a legal agreement between the federal Department of Energy, EPA and Washington’s Ecology Department, with an original cleanup deadline of 2016.

The building has been declared what’s called “slab-on-grade,” meaning the building above ground is demolished. But DOE says total cleanup of the project, including soil remediation and some core sampling underground, won’t be done until later this summer. 

Anna King calls Richland, Washington home and loves unearthing great stories about people in the Northwest. She reports for the Northwest News Network from a studio at Washington State University, Tri-Cities. She covers the Mid-Columbia region, from nuclear reactors to Mexican rodeos.